17 Avenue SE BRT Construction Update – June 9, 2017


Construction on 17 Avenue S.E. continues and this weekend the intersections of 37 Street and 45 Street and 17 Avenue S.E. will be closed for deep utility work. Detours will be set up at 36 and 38 Streets, as well as 44 and 47 Streets to direct traffic to 16 and 19 Avenues. Crews will be installing catch basins between 33 and 36 Street S.E. and asphalt paving will continue in the area as well.

Next week crews will be installing new sidewalks along the north side of 17 Avenue S.E. between 36 and 47 Streets, and the traffic detour will shift more to the south side of 17 Avenue S.E. between 36 and 47 Street.

Thank you for your continued patience as we work to make 17 Avenue a great space for everyone. For more details on the work happening over the next few weeks please see the attached update.