SE 17 Avenue Transitway Updates – April 6, 2018


Good afternoon –

Crews are getting ready to start construction on International Avenue in mid-April. Crews will be out working on traffic light bases at 42 and 33 Street, ENMAX will be doing utility work at 28 and 30 Street, and we’ll be prepping the roadway and detoured sections to get ready for construction.

In May we’ll be shifting westbound traffic between 26 and 30 Street S.E. to the south side of 17 Avenue S.E.
The BRT bridges are really taking shape and the girders have been installed on all three bridges. Over the next month crews will continue the work on the three bridges and the nearby retaining walls.

On April 14, the temporary traffic lights at 9 Avenue and 19 Street S.E. and at Blackfoot Trail and 19 Street S.E. will be activated. Later in April, a traffic detour will be set up for northbound traffic from 19 Street onto Blackfoot trail.

Don’t forget your favourite businesses on International Avenue will be open during construction, so make sure to stop by. Thank you for your patience as we work to make 17 Avenue a great space for everyone. For more details on the work happening over the next few weeks please see the attached update.

The BRT Project Team
The City of Calgary
calgary.ca/17avesebrt